The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.

The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.

TM Plan 1 and 2
23rd July Until 27th July — 1 Week

Will require 2-way light traffic signals on the road to carry out the storm outfall works

Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks

Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.

Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.

Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week

Will require road narrowing TM to carry out bell mouth remedial works to existing site access

TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks

Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.

TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks

Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works

TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks

Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works

TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks

Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works

TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks

Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting

All TM plans 1 to 10
26th November Until 30th November — 1 Week

Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works

popular recent storiesAlso in the news

Coop Cheque to High School
Haddenham Webteam: Thu 16 Sep 8:00pm

On Monday 13th September the Coop stores in Haddenham, Bedgrove, and Walton Court in collaboration presented a £600 Community Donation cheque towards AHS Aylesbury High School's racing and engineering projects.AHS has an e-power racing car team that competes in theregional races including Kop Hill Soap Box this month in Princes Risborough.The students are in the process of...

Feast Service
Haddenham Webteam: Wed 15 Sep 4:15pm

The long-standing tradition of holding a church service in association with the annual feast fair will return this coming weekend.The Churches Together in Haddenham Feast Service will take place on the green outside St Mary's Church on Sunday 19th September at 5.00pmIt will be led by Rev Cassa Masservy.All...

Fly Tip Rubbish
Haddenham Webteam: Wed 15 Sep 3:46pm

Having rubbish removed? Don't pay cash!Many of us are quite accustomed to paying 'cash-in-hand' to have odd jobs done to the house or in the garden — but if you ever need to have rubbish removed, this is the one time you should never pay cash.Did you know that your rubbish is far more likely to end up fly-tipped if you pay someone cash to remove it? A bona fide waste carrier...