
EventsUpcoming
NewsLatest














By Haddenham Webteam - 27th June 2018 11:45am
The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.
The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.
TM Plan 1 and 2
23rd July Until 27th July — 1 Week
Will require 2-way light traffic signals on the road to carry out the storm outfall works
Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks
Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.
Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.
Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week
Will require road narrowing TM to carry out bell mouth remedial works to existing site access
TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks
Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.
TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks
Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works
TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks
Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works
TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks
Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works
TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks
Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting
All TM plans 1 to 10
26th November Until 30th November — 1 Week
Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works
popular recent storiesAlso in the news

Staff on the Covid wards at Stoke Mandeville Hospital in Aylesbury have been thanked in the best way possible — with a welcome gift of two freezers that will enable them to grab some food during their busy shifts.Such are the pressures of working within the NHS at the moment, that staff are often unable to stop for meals and are using ice cubes as a way of staying hydrated during their busy...

Back in December 1993 the four Chrisitian churches (Anglican, Baptist, Catholic and Methodists) in the village of Haddenham held a special service during which a covenant (a set of promises) was established. It was a service that acknowledged our differences and celebrated the unique contribution brought by each tradition. But it was also a service that acknowledged that there was more that...

We have had a very busy and successful couple of days at the Stoke Mandeville Stadium Aylesbury Vaccination Centre. Most of our clinical team from Haddenham Medical Centre have been there at some point over this time both giving vaccines and in the really tricky work of vaccine preparation.The vaccines do not come prepared like flu jabs. There is an important, but painstaking, first stage of...