By Haddenham Webteam - 27th June 2018 11:45am
The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.
The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.
TM Plan 1 and 2
23rd July Until 27th July — 1 Week
Will require 2-way light traffic signals on the road to carry out the storm outfall works
Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks
Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.
Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.
Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week
Will require road narrowing TM to carry out bell mouth remedial works to existing site access
TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks
Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.
TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks
Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works
TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks
Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works
TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks
Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works
TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks
Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting
All TM plans 1 to 10
26th November Until 30th November — 1 Week
Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works
popular recent storiesAlso in the news

Does Haddenham need a Community Greengrocer?Blooming Fruity has been for sale for almost a year. It's possible that when sold it will cease to trade as a greengrocer. Regular users of the shop are concerned about this. The current owner's preferred option is to sell commercially as an ongoing greengrocer business. However, if this is not possible we have been preparing a contingency...

Haddenham and Thame EV Hire Club UpdateUsage is steadily increasing on the cars, and we keep receiving great feedback from Haddenham and Thame residents. The key reason for this scheme is to reduce emissions and help create cleaner air. Zero Carbon Haddenham have been calculating the mileage of both cars to see the positive effects of car sharing and using electric:Carbon Saving (March...

Florence Nightingale Hospice Charity — Fundraising EventSpring really started for the Haddenham Community Support Group (HCSG) with the coffee morning and flower arranging demonstration last week and will gather pace with the next event our Spring Fashion Show and Afternoon Tea. This will again be held at the popular Bradmoor Farm Function Suite on Thursday 20th April commencing at...