The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.

The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.

TM Plan 1 and 2
23rd July Until 27th July — 1 Week

Will require 2-way light traffic signals on the road to carry out the storm outfall works

Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks

Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.

Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.

Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week

Will require road narrowing TM to carry out bell mouth remedial works to existing site access

TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks

Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.

TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks

Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works

TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks

Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works

TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks

Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works

TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks

Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting

All TM plans 1 to 10
26th November Until 30th November — 1 Week

Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works

popular recent storiesAlso in the news

Carwithen Plaque Unvieled
Haddenham Webteam: Fri 01 Jul 3:00pm

The Carwithen Music Festival began on Friday 1st July — a celebration of Doreen Carwithen's centenary, here in Haddenham, her place of birth.Doreen Carwithen lived in the building in High Street, now owned by Peter and Margaret Aldington and housing the studios of photographer Paul Wilkinson.A blue plaque was unveiled there by Debbie Wiseman OBE, president of the festival and one of the...

Community Orchard Work Party
Haddenham Webteam: Wed 29 Jun 9:15am

The Community Orchard at Townsend Green has been undergoing some improvements recently to help wheelchair users and those with limited mobility access to the orchard and participate in events. The improvement work includes a new 'accessible gate', hard surface paths and raised beds that can be maintained by wheelchair users.The orchard improvement work is part of an approach to active...

Electric Vehicle
Diccon Proctor: Wed 29 Jun 9:00am

Zero Carbon Haddenham are hosting a stimulating talk on electric cars in the conference room at Haddenham village hall on Tuesday 5th July at 7.30pm. This will be a hybrid event (in person and via Zoom) and for the live talk you can turn up on the door without pre-booking. For the online version please sign in via this Eventbrite link: https://www.eventbrite.co.uk/e/climate...