Haddenham

Pegasus Way Traffic Management

Home » News » Pegasus Way Traffic Management
Traffic Congestion 01

The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.

The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.

TM Plan 1 and 2
23rd July Until 27th July — 1 Week

Will require 2-way light traffic signals on the road to carry out the storm outfall works

Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks

Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.

Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.

Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week

Will require road narrowing TM to carry out bell mouth remedial works to existing site access

TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks

Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.

TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks

Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works

TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks

Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works

TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks

Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works

TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks

Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting

All TM plans 1 to 10
26th November Until 30th November — 1 Week

Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works

popular recent storiesAlso in the news

Damien & Andy_Montage
David Finch: Wed 03 Jun 11:45am

Andy Coles & Damien Natale; Damien Natale & Andy Coles. However you say it, it's not possible to rationalise the events of Monday evening when the two great friends, cyclists and Sportive organisers from Haddenham both died whilst doing something they so very much enjoyed. Whether they were raising money for charity, creating and putting on events for others or just ensuring their mates had...

Scarecrow Festival 62
Francesca Flaxton: Sun 31 May 6:00pm

Haddenham Scarecrow Festival Open Monday 1st to Sunday 14th JuneTHANK YOU to everyone who has entered this year's Haddenham Association of Scouts & Guides' Scarecrow Festival. We have had a fantastic response with a record breaking 127 entries from all over Haddenham!! Our previous average has been 58 entries, with the highest number in 2018 of 71. In these very challenging times...

Robyn Thorogood
Robyn Thorogood: Sat 30 May 5:00pm

The end of May 2020 sees Robyn Thorogood retire after 27 years of managing Snakemoor Local Nature Reserve. Here he reflects on those years of service to the local communityIn 1993 Haddenham Parish Council (HPC) persuaded me to take on the management of Snakemoor but more about this later. Firstly, how did it all start?It was in 1987 that a few villagers visited Aylesbury Vale District...