The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.

The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.

TM Plan 1 and 2
23rd July Until 27th July — 1 Week

Will require 2-way light traffic signals on the road to carry out the storm outfall works

Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks

Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.

Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.

Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week

Will require road narrowing TM to carry out bell mouth remedial works to existing site access

TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks

Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.

TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks

Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works

TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks

Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works

TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks

Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works

TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks

Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting

All TM plans 1 to 10
26th November Until 30th November — 1 Week

Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works

popular recent storiesAlso in the news

Philippa Blowfield
Haddenham Webteam: Mon 28 Sep 2:00pm

Haddenham resident Dr Philippa Blowfield will be running the Official 40th London Marathon next Sunday, 4th October. Of course, due to Covid restrictions, the event cannot take place in London. So instead 45,000 runners across the world are running the distance in their local communities. You are likely to have spotted Philippa on her many training runs around Haddenham in the last few...

Dennis at Ivor Miles Garage
Haddenham Webteam: Sat 26 Sep 12:00pm

Dennis Vincent, the very longstanding fuel attendant at Ivor Miles garage in Churchway, has decided to retire after nearly 30 years' serving fuel to the motorists of Haddenham and the surrounding areas. Dennis has been an outstanding member of the Ivor Miles team and, in all weathers, been at the forefront of the business. Many local residents will recall that, despite his senior years...

Public Health England logo
Haddenham Webteam: Thu 24 Sep 4:30pm

The following letter is being distributed to parents and guardians from Public Health England:Dear parents and guardiansThis is an important letter to share some information on how we can work together to make sure we can continue to give children and young people the best education in the safest way possible.One important part of ensuring the safety and wellbeing of pupils, parents and...