The following details have been released to outline the Traffic Management Plans in respect of road works on Pegasus Way.

The originally notified duration has been extended — this is due to the time constraints that have been applied to these works (e.g 09.00 -16.00) to avoid peak hours.

TM Plan 1 and 2
23rd July Until 27th July — 1 Week

Will require 2-way light traffic signals on the road to carry out the storm outfall works

Road Narrowing Plan Phase 1
30th July Until 24th August — 4 weeks

Will require road narrowing TM as per Road Narrowing TM phase 1 to carry out the western access bell mouth works which include swale works i.e. installation of new culvert pipe and sand bag headwalls.

Due to having restricted room with road narrowing TM the projct manager doesn't believe contractors will be able to carry out the road widening works with road narrowing TM and will require lane closures with 2-way lights on the road to carry out these works.

Road Narrowing Plan Phase 2
28th August Until 31st August — 1 week

Will require road narrowing TM to carry out bell mouth remedial works to existing site access

TM Plan Phase 1 and 2
12th September Until 28th September — 2.5 Weeks

Will require 2 way lights on the road for carrying out the road widening works, installing new kerb line and installing new pedestrian crossing points.

TM Plan Phase 3 and 4
1st October Until 17th October — 2.5 Weeks

Will require 2 way lights on the road to carry out Road Widening, Kerbing, New footpath installation / amendments, Install Toucan crossing and street lighting works

TM Plan Phase 5 and 6
18th October Until 26th October — 1.5 Weeks

Will require 3 way lights on the road to continue Road Widening, Kerbing, and street lighting works

TM Plan Phase 7 and 8
29th October Until 9th November — 2 Weeks

Will require 2 way lights to carry out Installation of new footpath, amendments to current footpaths, Continue Road Widening, splitter islands, Kerbing, and street lighting works

TM Plan Phase 9 and 10
12th November Until 23rd November — 2 Weeks

Will require 3 way lights to continue Road Widening, Install new kerb line, re-dress verge, and street lighting

All TM plans 1 to 10
26th November Until 30th November — 1 Week

Will required Lane Closures with 2 way and 3 way to carry out final resurfacing and white lining works

popular recent storiesAlso in the news

NHS Image
Daniel Smith: Sat 23 Jan 6:30pm

Here are five ways you can help during the Covid pandemicThe NHS is under immense pressure due to the Covid pandemic.Its fantastic staff going above and beyond to keep us safe, so you may wish to show your thanks in ever more practical ways.While standing outside and cheering for our health workers is a good way to give appreciation, there are other ways to show your support for our...

Solar Panels Deal
Haddenham Webteam: Sat 23 Jan 5:30pm

Zero Carbon Haddenham has teamed up with an installer of PV solar panels in the hope of identifying a group of Haddenham residents who are keen to have solar power for their homes. Once a minimum group size has been extablished, the installation work can be carried out at a significant discount compared with one-off installations.The scheme is called Solar Streets.Solar panels charge...

Kaleidoscope Cheque
Haddenham Webteam: Sat 23 Jan 12:15pm

The members of Kaleidoscope would like to thank the residents of Haddenham and the surrounding villages for their very generous donations to the Sharing Life Trust which enabled them to hand over a cheque for £611.70 to one of their representatives last week. This will enable them to offer support in paying any urgent electricity bills needed by an increasing number of people...